East expansion of APC evaporation ponds - SP2-3 ( Part C)

Construction of a new evaporation pond (SP2-3), with an excavation volume of approximately 3.6 million cubic meters over a land area of 1.3 million square meters. The works also include the construction of a new dike with a length of 3.5 kilometers and also an earthen flood protection dam in the Numeira Wadi area.​

  • Project information:
     
  • Employer: Arab Potash Company Ltd. (APC)
  • Consultant: Royal Haskoning DHV
  • Value of project: 20 Million USD Dollars
  • Commencement date 01/08/2022.
  • Project Duration 940 days.
  • Contract Date for completion: 25/02/2025.
  • Project status: Completed on 21/07/2024.